Press Release
For Immediate Release
23 August 2006
Contact: Craig Cox, 303-679-9331
New Study: Wind Energy Saves Gas,
Cuts Consumer Electric Costs
“Backcasting” Report Shows Additional
263 Megawatts of Wind could be Added
Conifer, Colo. — A trailblazing new study released by
the Interwest Energy Alliance reports that consumers
will save more than $251 million because of Xcel
Energy’s current fleet of wind plants over the coming
two decades. The study further concludes that consumers
could have saved another $186 million had Xcel invested
in more wind during three recent bidding cycles for new
electric generators.
By comparing existing wind projects and wind projects
that were proposed (but not built) to the cost of
natural gas generation (which wind energy most often
displaces), the authors of this study, Jane Pater and
Ron Binz, quantify savings that wind energy generation
has already provided Xcel Energy’s consumers. The
authors then project what consumers would have saved if
additional amounts of wind energy generation that Xcel
sought but did not buy had been added to Xcel’s power
generation portfolio during generation resource
acquisition bids in 1999, 2004 and 2005. Pater is
experienced in energy and environmental affairs, and
Binz was Colorado Consumer Counsel for eleven years.
The study’s findings —that more wind means more
consumer savings— are also significant because Xcel’s
own research shows that it can cost-effectively and
reliably accommodate wind energy up to about 15% of its
electric generation totals, about twice as much as it
currently has on its system or has recently agreed to
purchase. Last year Xcel announced it would enter into
agreements to buy the output from 775 additional
megawatts of new wind energy. The Pater-Binz study
reports that Xcel could add another 263 MW of wind next
year to reach a penetration level of 15%. “A 15% wind
level would deliver even more cost savings to its
consumers, along with significant environmental and
economic benefits to the whole state,” said Fred Hefley,
manager of Baca Green Energy in Walsh, Colorado.
Xcel’s failure to add the wind energy that could be
benefiting its electric customers now has been
attributed to lack of transmission lines to bring the
wind from Colorado’s windy Eastern Plains to Front Range
electric loads. Xcel’s plans for new transmission, just
announced to transmission planners and a legislative
transmission study committee, do not address large
amounts of new wind energy. Since transmission takes
five to seven years to build, while wind plants can be
built in a year or two, Xcel customers will have to wait
for the transmission to be planned and built to get new
wind plants to provide relief from high natural gas and
electric prices.
The Interwest Energy Alliance emphasized that in
order for Colorado to harness the tremendous potential
for wind power —and reap its multifaceted benefits—
much-needed electric transmission infrastructure must be
developed to bring wind-generated electricity to load
centers. “More transmission from Colorado’s eastern
plains wind resources would help struggling rural
communities reap economic benefits from investment and
jobs in wind plants, while Front Range consumers would
have access to cleaner, more secure and lower cost
electricity,” said Ron Lehr, attorney and former
Colorado PUC Chairman who now represents the wind
industry. “It’s time to ‘connect the dots,’ get
transmission planned and built, and bring wind power
benefits to the whole state.”
Significant findings from this study include:
- The cost savings for wind generation that Xcel
Energy has already acquired will produce more than
$251 million in fuel and emissions cost savings for
PSCo ratepayers over the next 20 years.
- Had Xcel acquired additional wind generation that
it sought and was offered, at about the prices for the
wind it did buy, Colorado ratepayers would have saved
a total of $438 million over the lives of these
contracts (15 to 20 years) —that is, an additional
$186 million over the savings that will be achieved by
the wind farms now on the Xcel system.
- Current levels of wind generation will prevent
19.2 million tons of carbon dioxide that would
otherwise result from burning fossil fuels; adding
wind generation that could have been purchased, as
suggested in this study, would have further reduced
carbon dioxide emissions by 14.7 million tons.
To read the entire study, entitled “Wind on the
Public Service Company of Colorado System: Cost
Comparison to Natural Gas,” visit the Interwest Energy
Alliance’s website at
www.interwest.org.
The Interwest Energy Alliance is a
trade association that represents the nation’s leading
companies in the wind energy industry, bringing them
together with some of the West’s leading
non-governmental organizations to facilitate
consensus-based approaches to new project development
and transmission issues throughout the region. |